Narrabri township is on Level 3 water restrictions with exemptions made on Friday,1 May 2026
The Violet Street Bridge remains closed until November 2026 for bridge replacement works. A detour is in place along Selina Street, Newell Highway and Tibbereena Street.
Published on 13 July 2026
Violet Street Bridge replacement project
Following the completion of foundation piling works, pier piles are being cut down to the design level, with steelwork for pile caps underway.
The old bridge piers, which were used to support the temporary pile guide frames, will be demolished in mid-July.
The bridge’s next milestone will include the construction of the pile caps, blade piers and the abutment at the Selina Street end of the bridge. This is expected to take around six weeks.
Construction of the headstocks and placement of the girders will then take place.
More information about the Violet Street Bridge replacement can be found on the project’s website.