Major Projects updates

Find out more about the range of major projects happening across our Shire, including the latest updates.

Greenhill's Quarry extension

Narrabri Shire Council is currently progressing approvals for the continued operation and proposed extension of the existing Greenhill's Quarry on Old Narrabri Road, Narrabri.

This project will provide materials to support Council's ongoing road maintenance program across the Shire.  

Any questions in relation to this project can be directed to Council's Manager Road Services Michael Cain on 02 6799 6866.

Wee Waa Community Precinct

At the 2026 September Ordinary Council Meeting, Council endorsed a new concept design for the site formerly proposed as the Wee Waa Community and Business Centre.

It follows a Notice of Motion from Cr. Towns in May and feedback from the wider Wee Waa community, where Council investigated options for a revised project scope.

As the project is grant-funded, Council will now return to the funding body with the revised scope for approval.

While the design has changed, the purpose of the project remains the same - creating a space for the Wee Waa community to gather, connect and celebrate.

Narrabri Waste Management Facility Expansion

The Narrabri Waste Management Facility expansion is complete. 

The project includes the construction of two adjoining landfill cells (Cell 2 and Cell 3) and associated infrastructure. Additionally, the project includes:

  • Site establishment
  • Construction of sediment control basin
  • Construction of the leachate pond
  • Construction of Cells 2 and 3

This expansion will continue to support landfill operations within the existing site and meet the Shire's future waste management requirements.

Following a Confidential Report at the December 2025 Ordinary Council Meeting, the tender for the Construction of Expansion Cells 2 and 3 at the Narrabri Waste Management Facility was awarded to Synergy Resource Management Pty Ltd.

For any further information, please contact the Narrabri Shire Council on (02) 6799 6866 or council@narrabri.nsw.gov.au

Violet Street Bridge replacement project

The new Violet Street Bridge is nearing completion, with works focusing on final elements including pathway connections, street lighting and road approaches. 

Subject to favourable weather conditions, the bridge is anticipated to open to traffic and pedestrians in early December.

A detour remains in place along Selina Street, Newell Highway and Tibbereena Street for the duration of works.

The Violet Street Bridge replacement project will see the removal of the existing Violet Street Bridge over Narrabri Creek and replaced with a steel reinforced concrete structure as well as new road approaches.

The new bridge will feature:

  • Dual traffic lanes
  • Shared pathway for pedestrians and cyclists on each side of the bridge
  • Unrestricted heavy vehicle access
  • New overhead street lighting

The new structure will also decrease the time required to remove barriers during flood events. This means the bridge will not need to close as early as per previous flood events – reducing disruption for residents and road users. 

Council continues to assist those directly affected by the works, including residents, the local school, bus companies, businesses and emergency services.

The $7.5 million Violet Street Bridge replacement project has been made possible with the contribution of $5 million through the Infrastructure Betterment Program jointly funded by the Australian and NSW Governments under the Disaster Recovery Funding Arrangements. 

The Australian Government’s Roads to Recovery Program contributed the remaining $2.5 million for the project.

For more information, including indicative timelines, FAQs and more, please visit the project’s website.

PFAS portable water treatment plant

Councillors endorsed a proposal to procure a temporary water treatment plant to bring the Killarney Bore back online, providing security against PFAS contamination from this bore in the water supply for Narrabri.

The temporary treatment plant will be procured utilising the NSW Government’s $4 million PFAS Emergency grant.

Procurement and installation of the temporary water treatment plant is subject to endorsement from the Department of Climate Change, Energy, the Environment and Water (DCCEEW). 

In November 2025, Council welcomed a $4 million commitment from the NSW Government to deliver a portable water treatment plant and new production bores for the Narrabri township.

Narrabri bore investigation project

Saleyards Lane Bore

A licence application to modify Narrabri’s Town Water Access Licence to include the Saleyards bore has been approved by the DCCEEW.

Initial investigations indicate the bore water may require additional treatment before it can be added to the water supply.  

Council is working with NSW Health to determine the suitability of bringing the Saleyards Lane bore online.

Logans Lane Bore

Following confirmation from a Registered Surveyor that the bore is located within the Logans Lane road reserve, Council has engaged a contractor to complete a 72-hour pumping test, analysis and reporting to confirm its suitability as an additional/alternate water production bore.

It’s also collecting a number of water samples to ensure the quality of the water.

A report will then be provided to NSW Health for review on the suitability of the supply at the location. 

Rangari Road sealing

Construction of the new causeway reached a major milestone with the completion of concrete works. Crews have now commenced work on erosion protection measures downstream of the crossing.

Current works include:

  • Completion of erosion protection works downstream of the causeway.
  • Final earthworks around the new causeway.
  • Installation of new depth marker signage.

Once the concrete has fully cured, the new causeway is expected to reopen to traffic in early December, followed by the removal of the temporary sidetrack.

Following completion of the causeway, work will continue on drainage improvements and the 9.6km road upgrade, which is scheduled to commence in the new year.

Motorists are reminded to follow all traffic control measures and take care when travelling through the works area.

The Rangari Road project will include:

  • Sealing of the remaining 10 kilometres of unsealed road.
  • Road widening.
  • Improved drainage.
  • Upgraded signage.
  • New intersection and centre line markings.
  • New guideposts.
  • Enhanced delineation throughout the route.

The $9 million project has been made possible through the NSW Government’s Rural and Regional Roads Fund. 

Learn more about the Rangari Road upgrade.

Violet Street water main upgrade

Council is upgrading around 226m of water main in Violet Street from the Tibbereena Street intersection as part of the Violet Street Bridge Replacement Project.

Current works on Violet Street have provided an opportunity to replace this critical piece of pipe infrastructure, which is over 50 years old.

The new 300mm pipe will help accommodate increased water demand associated with anticipated development and population growth in areas west of Narrabri Creek.

Turrawan Road works

Following rehabilitation, heavy patching and resealing, finalisation of works are taking place on Turrawan Road. 

This includes completion of drainage, guide posting, final works on the traffic island at the Maules Creek Road intersection and line marking.

We thank our community for their patience during finalisation of these works. 

Sewer mains maintenance and repairs

Underground Experts are carrying out maintenance and repairs to sewer mains between Namoi Creek and the Namoi River. 

These important works will help maintain the sewer network and support reliable sewerage services for the community.

The project will include:
  • Cleaning and CCTV inspection of sewer mains
  • Sewer main relining
  • Reinstatement of work sites

Residents directly affected by the works will receive a letter before work begins.

Work hours:
  • Monday to Friday: 7.00am to 6.00pm
  • Saturday: 8.00am to 5.00pm

During the works, residents may notice:

  • An increase in noise
  • More vehicle movements
  • Occasional odours
  • Temporary impacts on footpaths, roads and parking

If any road or footpath closures are required, appropriate traffic management will be in place to help keep the community safe.

The project is expected to be completed in January 2027.

We thank the community for your understanding while this work is underway.

Reseal program

Road resealing works are nearing completion, with crews expected to finish works on Old Gunnedah Road in late November (weather permitting).

Works on Kaputar Road will be completed at a later date during warmer weather, while resealing on Old Turrawan Road will take place after completion of planned road works. 

Works planned for Old Turrawan Road will involve shoulder widening and resealing between the railway line and Gordon Roadways.

Council will provide an update once timing for these works has been confirmed.

Please remember to follow signage and directions from traffic controllers around work sites and drive with care.

We thank our community for your patience and cooperation while these works are carried out.