Narrabri township is on Level 3 water restrictions with exemptions made on Friday,1 May 2026
The Violet Street Bridge remains closed until November 2026 for bridge replacement works. A detour is in place along Selina Street, Newell Highway and Tibbereena Street.
Published on 17 June 2026
Violet Street Bridge replacement project
Piling works are continuing on foundations for the new Violet Street bridge, with driving of Pier 1 piles underway.
This will be followed by Abutment A piling works.
Abutment B, Pier 3 and Pier 2 piles are in place. Construction of Abutment B is also in progress.
Rangari Road sealing
The tender for tree removal as part of the Rangari Road upgrade has closed. The tender for the project's Bayley Park Creek Causeway construction and associated works is open until 11.00am Tuesday, 14 July 2026.