Narrabri township is on Level 3 water restrictions with exemptions made on Friday,1 May 2026
The Violet Street Bridge will be closed from Monday, 19 January to the end of September 2026 for bridge replacement works. A detour will be in place along Selina Street, Newell Highway and Tibbereena Street.
Published on 23 June 2026
Violet Street Bridge replacement project
Piling works are continuing on foundations for the new Violet Street Bridge, with Pier 1 completed. Abutment A is scheduled to be completed by late this week. This will complete all piling works associated with the new bridge.
Pier 2 and Pier 1 piles will then be cut down to the design level, while the concrete pour for Abutment B is scheduled for this week.
Steelwork for the pile caps for each pier is also currently in progress. The existing bridge piers that have been used to support the temporary pile guide frames are scheduled to be demolished in mid-July.
More information about the Violet Street Bridge replacement can be found on the project’s website.
Roads Maintenance Schedule - week commencing 22 June 2026
Grading
Jet patching
Hand patching
Waste
Airport
Parks and Open Spaces
Narrabri parks
Boggabri
Wee Waa
Pilliga
Gwabegar
Water/Sewer